The Wideman Comparative Glossary of Common Project Management Terms describes estimating cost as, "the process of forecasting a future result in terms of cost, based upon information available at the time."

In his book 'How to be a Better Project Manager', Trevor L Young defines estimating as "A decision about how much time and resource are required to carry out a piece of work to acceptable standards of performance."

Many techniques, books and software packages exist to help with estimating project costs. A few simple rules will also help ensure you create an accurate and realistic estimate.

  • Assume resources will only be productive for 80 percent of their time.
  • Resources working on multiple projects take longer to complete tasks because of time lost switching between them.
  • People are generally optimistic and often underestimate how long tasks will take.
  • Make use of other people's experiences and your own.
  • Get an expert view.
  • Include management time in any estimate.
  • Always build in contingency for problem solving, meetings and other unexpected events.
  • Cost each task in the Work Breakdown Structure to arrive at a total, rather than trying to cost the project as a whole.
  • Agree a tolerance with your customer for additional work that is not yet defined.
  • Communicate any assumptions, exclusions or constraints you have to your customer.
  • Provide regular budget statements to your customer, copying your team, so they are always aware of the current position.

Much data exists about the length of time particular items of work take, especially in the construction industry. A useful database of production rates can be found atPlanning Planet 

Common Mistakes

These are some of the common mistakes that can lead to inaccurate estimates.

  • Not understanding what is involved to complete an item of work.
  • Starting with an amount of money and making the project cost fit it.
  • Assigning resources at more than 80 percent utilisation.
  • Failing to build in contingency.
  • Failing to adjust the estimate following changes in scope.
  • Dividing tasks between more than one resource.
  • Providing estimates under pressure in project meetings.
  • Giving single-data-point estimates rather than range estimates.

Three Point Estimating

Three point estimating is a technique that helps project managers produce better estimates. Rather than a ballpark estimate, project managers can use three point estimating to gain a greater degree of control over how the end value is calculated. The end value is the weighted average of three estimates.

To do three point estimating for a particular task or activity, ask the resource for their best-case, most likely and worst case estimates. Add the best-case estimate to four times the most likely, then the worst case and divide by six. This gives you your estimate (E value) which is a slightly more balanced view of how long the task or activity is likely to take.

The formula is expressed as:

E = (B + 4 M + W)/6

  • B = best-case (1/6)
  • M = most likely (4/6)
  • W = worst case (1/6)

Estimating Project Costs的更多相关文章

  1. Project Management Process

    Project Management ProcessDescription .............................................................. ...

  2. 10 Golden Rules of Project Risk Management

    The benefits of risk management in projects are huge. You can gain a lot of money if you deal with u ...

  3. PMP模拟考试-2

    1. Increasing resources on the critical path activities may not always shorten the length of the pro ...

  4. PMP用语集

    AC actual cost 实际成本 ACWP actual cost of work performed 已完工作实际成本 BAC budget at completion 完工预算 BCWP b ...

  5. PMBOK及PMP考试精要

    PROJECT MANAGEMENT KNOWLEDGE AREAS项目管理知识体系 2 PROJECT LIFE CYCLE / PROJECT MANAGEMENT PROCESS GROUPS项 ...

  6. P6 Professional Installation and Configuration Guide (Microsoft SQL Server Database) 16 R1

    P6 Professional Installation and Configuration Guide (Microsoft SQL Server Database) 16 R1       May ...

  7. 对比其它软件方法评估敏捷和Scrum

    一般来说,选择一种软件开发方法,更像是加入一个邪教组织,而不像是做出了一个技术决策.许多公司甚至从未试图去评估这些方法,而仅仅是盲目采用最流行的方法,这就造成了如今五花八门的各种敏捷方法.因此本文将使 ...

  8. 2017.10.30 Epicor -ERP

    1 公司新用ERP系统,做使用培训,mark... This course reviews the project management flow in the Epicor application. ...

  9. 12 Tips for Accurate Project Estimating

    Projects typically involve many dynamic aspects, yet they're often constrained by finite conditions. ...

随机推荐

  1. JavaScript_判断浏览器种类IE、FF、Opera、Safari、chrome及版本

    function myBrowser(){ var userAgent = navigator.userAgent; //取得浏览器的userAgent字符串 var isOpera = userAg ...

  2. git 创建branch分支

    开发者user1 负责用getopt 进行命令解析的功能,因为这个功能用到getopt 函数,于是将这个分支命名为user1/getopt.(1)确保是在开发者user1的工作区中cd /home/j ...

  3. List 中对象属性排序

    有几个方法可以实现:让 Student 实现Comparable接口,或是实例化一 个比较器, 现在用 Comparator 比较器实例来做一个:ComparableTest.java import  ...

  4. 【C语言】04-函数

    一.函数的分类 前面已经说过,C语言中的函数就是面向对象中的"方法",C语言的函数可以大概分为3类: 1.主函数,也就是main函数.每个程序中只能有一个.也必须有一个主函数.无论 ...

  5. debug阶段工作期站立会议2(进度推进)

    组名:天天向上 组长:王森 组员:张政.张金生.林莉.胡丽娜 代码地址:HTTPS:https://git.coding.net/jx8zjs/llk.git SSH:git@git.coding.n ...

  6. laravel transaction : laravel 的事务是不支持eloquent的, 要用DB::的方式

    数据库事务处理# 你可以使用 transaction 方法,去执行一组数据库事务处理的操作: DB::transaction(function() { DB::table('users')->u ...

  7. UItableview section和cell的局部刷新

    局部刷新//一个section刷新    NSIndexSet *indexSet=[[NSIndexSet alloc]initWithIndex:2];    [tableview reloadS ...

  8. 【翻译】西川善司「实验做出的游戏图形」「GUILTY GEAR Xrd -SIGN-」中实现的「纯卡通动画的实时3D图形」的秘密,前篇(2)

    Lighting和Shading(2)镜面反射的控制和模拟次级表面散射技术 http://www.4gamer.net/games/216/G021678/20140703095/index_2.ht ...

  9. DWZ的选择带回功能无法带回第一个value中的值

    <volist name="node1._child" id="node2"> 这里的value中第一个id是无法带回给上一个页面的..如果要带回则 ...

  10. 图文解说:Nginx+tomcat配置集群负载均衡

    图文解说:Nginx+tomcat配置集群负载均衡 博客分类: appserver nginxTomcatUbuntuLinux网络应用  作者:niumd Blog:http://ari.iteye ...