Estimating Project Costs
The Wideman Comparative Glossary of Common Project Management Terms describes estimating cost as, "the process of forecasting a future result in terms of cost, based upon information available at the time."
In his book 'How to be a Better Project Manager', Trevor L Young defines estimating as "A decision about how much time and resource are required to carry out a piece of work to acceptable standards of performance."
Many techniques, books and software packages exist to help with estimating project costs. A few simple rules will also help ensure you create an accurate and realistic estimate.
- Assume resources will only be productive for 80 percent of their time.
- Resources working on multiple projects take longer to complete tasks because of time lost switching between them.
- People are generally optimistic and often underestimate how long tasks will take.
- Make use of other people's experiences and your own.
- Get an expert view.
- Include management time in any estimate.
- Always build in contingency for problem solving, meetings and other unexpected events.
- Cost each task in the Work Breakdown Structure to arrive at a total, rather than trying to cost the project as a whole.
- Agree a tolerance with your customer for additional work that is not yet defined.
- Communicate any assumptions, exclusions or constraints you have to your customer.
- Provide regular budget statements to your customer, copying your team, so they are always aware of the current position.
Much data exists about the length of time particular items of work take, especially in the construction industry. A useful database of production rates can be found atPlanning Planet
Common Mistakes
These are some of the common mistakes that can lead to inaccurate estimates.
- Not understanding what is involved to complete an item of work.
- Starting with an amount of money and making the project cost fit it.
- Assigning resources at more than 80 percent utilisation.
- Failing to build in contingency.
- Failing to adjust the estimate following changes in scope.
- Dividing tasks between more than one resource.
- Providing estimates under pressure in project meetings.
- Giving single-data-point estimates rather than range estimates.
Three Point Estimating
Three point estimating is a technique that helps project managers produce better estimates. Rather than a ballpark estimate, project managers can use three point estimating to gain a greater degree of control over how the end value is calculated. The end value is the weighted average of three estimates.
To do three point estimating for a particular task or activity, ask the resource for their best-case, most likely and worst case estimates. Add the best-case estimate to four times the most likely, then the worst case and divide by six. This gives you your estimate (E value) which is a slightly more balanced view of how long the task or activity is likely to take.
The formula is expressed as:
E = (B + 4 M + W)/6
- B = best-case (1/6)
- M = most likely (4/6)
- W = worst case (1/6)
Estimating Project Costs的更多相关文章
- Project Management Process
Project Management ProcessDescription .............................................................. ...
- 10 Golden Rules of Project Risk Management
The benefits of risk management in projects are huge. You can gain a lot of money if you deal with u ...
- PMP模拟考试-2
1. Increasing resources on the critical path activities may not always shorten the length of the pro ...
- PMP用语集
AC actual cost 实际成本 ACWP actual cost of work performed 已完工作实际成本 BAC budget at completion 完工预算 BCWP b ...
- PMBOK及PMP考试精要
PROJECT MANAGEMENT KNOWLEDGE AREAS项目管理知识体系 2 PROJECT LIFE CYCLE / PROJECT MANAGEMENT PROCESS GROUPS项 ...
- P6 Professional Installation and Configuration Guide (Microsoft SQL Server Database) 16 R1
P6 Professional Installation and Configuration Guide (Microsoft SQL Server Database) 16 R1 May ...
- 对比其它软件方法评估敏捷和Scrum
一般来说,选择一种软件开发方法,更像是加入一个邪教组织,而不像是做出了一个技术决策.许多公司甚至从未试图去评估这些方法,而仅仅是盲目采用最流行的方法,这就造成了如今五花八门的各种敏捷方法.因此本文将使 ...
- 2017.10.30 Epicor -ERP
1 公司新用ERP系统,做使用培训,mark... This course reviews the project management flow in the Epicor application. ...
- 12 Tips for Accurate Project Estimating
Projects typically involve many dynamic aspects, yet they're often constrained by finite conditions. ...
随机推荐
- android 蓝牙4.0多通道
很久没记录东西了,前段时间研究了一哈android4.0控制多个外设的情况,注意,需要使用android版本4.3以上,蓝牙4.0及以上. 我这里使用的控制蓝牙灯泡,使用android4.3的手机,手 ...
- 【BZOJ】3850: ZCC Loves Codefires(300T就这样献给了水题TAT)
http://www.lydsy.com/JudgeOnline/problem.php?id=3850 题意:类似国王游戏....无意义.. #include <cstdio> #inc ...
- iOS移动开发周报-第22期
iOS移动开发周报-第22期 [摘要]:本期iOS移动开发周报带来如下内容:苹果股价创新高,iOS8自动调整UITableView布局,Swift学习心得等. 新闻 <苹果股价创新高 市值全球第 ...
- php 配置正确的时间
关于php时区时间错误问题 date 当前时间 时差 当地 本地date_default_timezone_set 之前有一个遗留问题,就是echo date("y-m-d h:i:s&qu ...
- PAT天梯赛练习题 L3-011. 直捣黄龙(多关键字SPFA+DFS)
L3-011. 直捣黄龙 时间限制 150 ms 内存限制 65536 kB 代码长度限制 8000 B 判题程序 Standard 作者 陈越 本题是一部战争大片 —— 你需要从己方大本营出发,一路 ...
- 移动WEB 性能优化方案
最近一项 研究表明,80%的网民对移动端的浏览体验感到失望,同时,当体验提升时,他们会在智能手机上花费更多的时间. 这不奇怪,因为64%的智能手机用户希望网站可以在4秒内加载完毕,但一半的网站花费了二 ...
- 【翻译】西川善司「实验做出的游戏图形」「GUILTY GEAR Xrd -SIGN-」中实现的「纯卡通动画的实时3D图形」的秘密,前篇(2)
Lighting和Shading(2)镜面反射的控制和模拟次级表面散射技术 http://www.4gamer.net/games/216/G021678/20140703095/index_2.ht ...
- DWZ的选择带回功能无法带回第一个value中的值
<volist name="node1._child" id="node2"> 这里的value中第一个id是无法带回给上一个页面的..如果要带回则 ...
- 送给和我一样曾经浮躁过的PHP程序猿
送给和我一样曾经浮躁过的PHP程序猿 2012年偶决定开始写博客了,不为别的,就希望可以通过博客记录我的成长历程,同时也希望可以帮助一些刚毕业,刚入行业的兄弟姐们 们.我们是一群充满浮躁.抱怨.迷 ...
- 为什么我的联想打印机M7450F换完墨粉之后打印机显示请更换墨粉盒?这是我的墨盒第一次灌粉·、
需要打印机清零,可以网上查到的,要不就去买颗芯片换上关掉机器 →开机的同时按住功能按扭不松手开机→进入维修模式→翻到84功能项→按OK→用下翻键找到PROCESS CHECK→按OK 按扭→关机→正常 ...