One of the challenges of explaining project management to people who are unfamiliar with the approach, is that descriptions are often either so high-level as to be meaningless, or so detailed that they are overwhelming. Over the years, I have come to use a model as a framework for introducing and discussing project management tools and techniques. It can be used as the basis for a five-minute explanation of what is involved in project management, but also as an outline for more detailed discussions. (The actual model can be found on the Key Consulting website under free templates and info.)

A brief description of each step follows:

Assemble Team

The project planning team will be assembled, including appropriate representation from customers/clients, and sometimes subcontractors and vendors. Initial roles and responsibilities will be defined.

Deliverables: Initial project setup documentation.

Define Project Objective

With the project team in place, the overall project purpose will be verified and detailed project objectives developed. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is planning.

Deliverables: project charter, phase-exit review checklist.

Define Project Scope

An appropriately detailed Work Breakdown Structure (WBS) will be developed to ensure the project scope is properly agreed to and understood by all stakeholders. This also allows the complete project to be split into appropriate sub-projects and/or phases.

Deliverables: Project work breakdown structure.

Construct an Initial Plan

Once tasks of an appropriate level have been identified in the WBS, they will be organised by the project team into logical network diagrams, with estimated durations. This allows the project manager to predict when activities will be complete, assess the feasibility of target dates, and identify the critical path for the project.

Deliverables: Initial work plan.

Add Resources, Costs, Risks, etc.

Certain project resources may be defined as critical resources. In particular, the project manager may suspect that key project staff may be faced with too much work. If so, estimated resource usage information can be added to the project plan to allow resource forecasting. Cost is obviously also critically important, and expenditures can be added to the plan to create estimated cash-flow requirements. Risk management can also be utilised on projects to provide a framework to better manage events that occur beyond the control of the project team.

Deliverables: Resource availability and commitment profiles, risk identification and control strategies, cash-flow forecasts.

Obtain Stakeholder Buy-in

To ensure the project is implemented as smoothly as possible, with the support of the involved parties, it will be necessary to review the initial plans with all the major project stakeholders and to solicit buy-in from each one. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is control.

Deliverables: Approved final plan, phase-exit review checklist.

Publish the Plan

Once the plans are agreed to, they must be effectively communicated to all stakeholders. This can be done in hard copy or via electronic media, depending on the resources available. On most projects, a communications plan will be developed, and distribution of the plans will follow the guidelines laid out in the communications plan.

Deliverables: Plan published to all stakeholders.

Collect Progress Information

On a regular basis, the project manager will collect progress information that has been reported by the project team. This will allow the compilation of progress reports, such as:

  • Activities completed within the past two weeks.
  • Activities forecast for the next two weeks with a focus on activities on the critical path.
  • Funds expended vs. fund expenditure forecast.
  • Prioritised issues report.

Metrics can also be developed to measure project progress in other ways, such as earned value, or activity float statistics. If the project manager reviews the progress data and concludes that the project is complete, a phase-exit review will be completed to confirm that all the objectives have been met before moving into the final closure phase.

Deliverables: Set of progress reports, set of exception reports, metrics report, (phase-exit review checklist).

Analyse Current Status

By analysing the progress information received, the project manager will be able to augment the above reports with information about which areas of the project are of concern and where problems are likely to occur in the future. This allows managers to focus on the important/critical areas of the project.

Deliverables: Project evaluation report(s).

Adjust the Plan, and Manage Project Change

Based on the analysis, and with the support of the project team, the project manager will make plan adjustments to help reduce risks, accommodate scope changes, or to compensate for activities that have not occurred on schedule. Once this has happened, the plan will re-published and the cycle repeated until the project is complete.

Deliverables: Change request forms, updated plan.

Close Project

When the objectives of the project have been achieved, the project manager will close down the project. This will involve some financial closure tasks, as well as archiving of the project materials. A lessons-learned document will be developed to benefit future projects, and if possible a project team celebration will be held.

Deliverables: Final project report including lessons learned.

The Simplified Project Management Process的更多相关文章

  1. Project Management Process

    Project Management ProcessDescription .............................................................. ...

  2. Introduction to Project Management(II)

    Introduction The purpose of this paper is to gain an understanding of project management and to give ...

  3. Introduction to Project Management(I)

    Project management in the modern sense began in the early 1950s, although it has its roots further b ...

  4. 【转】bug management process

    What is Bug? A bug is the consequence/outcome of a coding fault What is Defect? A defect is a variat ...

  5. 简介 - PMP(Project Management Professional)

    PMP(Project Management Professional) 官网(英文报名):https://www.pmi.org/ 中文注册:http://exam.chinapmp.cn/ Boo ...

  6. 10 Rules of Highly Successful Project Management

    I commited the information below to report PDU of PMI. ^_^. In this paper, the author introduces his ...

  7. Software Engineering: 2. Project management

    resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...

  8. Software Project Management hw1

    I just want to say something about my java project that I did last year. Our task is to finish a lin ...

  9. Linux Process Management && Process Scheduling Principle

    目录 . 引言 . 进程优先级 . 进程的生命周 . 进程表示 . 进程管理相关的系统调用 . 进程调度 . 完全公平调度类 . 实时调度类 . 调度器增强 . 小结 1. 引言 在多处理器系统中,可 ...

随机推荐

  1. asp.net 微信企业号办公系统-流程设计--保存与发布

    如果流程未设计完时可以先保存,以后再打开接着设计.点击工具栏上的保存按钮即可保存当前流程设计: 如果下次要接着设计,则可以打开该流程继续设计: 如果流程设计完成,可以点击安装按钮来发布流程,流程安装成 ...

  2. 【C语言】14-返回指针的函数与指向函数的指针

    前言 前面我们花了接近3个章节学习指针,应该都感受到指针的强大了吧.指针可以根据地址直接操作内存中的数据,使用得当的话,不仅能使代码量变少,还能优化内存管理.提升程序性能.关于指针的内容还非常多,比如 ...

  3. smarty模板中literal标签的使用

    在使用的时候把js等代码写在模板中就报错,加入literal标签后就正确了 <style> {literal} .tr_color{background-color: #9F88FF} { ...

  4. MONGODB 计算机服务

    安装完成后,在 BIN目录执行如下 E:\APMServ5.2.6\MongoDb\bin>mongod --logpath E:\APMServ5.2.6\MongoDb\logs\Mongo ...

  5. 暑假训练round 3 题解

    今天做题运气出奇的好,除了几处小错误调试之后忘记改掉了……最后还AK了……虽然题目不难,学长也说是福利局,但是对个人的鼓励作用还是挺大的……至此暑假训练就结束了,也算没有遗憾……. 题解如下: Pro ...

  6. java字符串练习题

  7. Note: RewriteCond规则

    如果文件存在,就直接访问文件,不进行下面的RewriteRule:RewriteCond %{REQUEST_FILENAME} !-f 如果目录存在,就直接访问目录,不进行下面的RewriteRul ...

  8. 语艺杂谈1 – MAP赋值与插入

    MAP赋值和插入,对于相同ID的处理方式不同,前者为替换 后者为插入失败 #include <map> #include <string> #include <iostr ...

  9. 神奇的 echo 命令

    #!/bin/bash 请输入密码,输入密码的时候不能看见因为颜色设置成跟背景色一样了,输入完密码进行加密,加密后保存在pass.txt echo "Please input a passw ...

  10. JAVA分支语句例题

    1.输入年份判断是闰年还是平年? System.out.println("请输入年份:"); Scanner sc=new Scanner(System.in); String s ...