Const init_info As String = "InitInfo"
Const end_row_op As Integer = 100  'tmp
Const end_row_holiday As Integer = 100  'tmp
Const sheet_name_op As String = "Project_YY"  'tmp
Const sheet_name_holiday As String = "Holiday"  'tmp
Const column_index_task As Integer = 3 'tmp
Const column_index_cost As Integer = 5 'tmp
Const column_index_start_date As Integer = 6 'tmp
Const column_index_end_date As Integer = 7 'tmp
Const column_index_man As Integer = 8 'tmp
Const column_index_sort As Integer = 9 'tmp
Const column_index_holiday As Integer = 2 'tmp
Const column_index_workday As Integer = 3 'tmp

Function is_date_in_col(ByVal sheet_name As String, ByVal col As Integer, ByVal value As Date) As Integer
    Dim end_row As Integer
    end_row = end_row_holiday 'tmp  get_row_range
    
    Dim test_row As Integer
    Dim ret As Integer
    is_date_in_col = 0
    
    Dim col_date As Date
    
    For test_row = 3 To end_row
        col_date = Sheets(sheet_name).Cells(test_row, col).value
        If value = col_date Then
            is_date_in_col = test_row
            Exit For
        End If
    Next
End Function

Function is_date_in_holiday_list(ByVal in_date As Date) As Boolean
    
    If is_date_in_col(sheet_name_holiday, column_index_holiday, in_date) <> 0 Then
        is_date_in_holiday_list = True
    Else
        is_date_in_holiday_list = False
    End If
    
End Function

Function is_date_in_workday_list(ByVal in_date As Date) As Boolean
    
    If is_date_in_col(sheet_name_holiday, column_index_workday, in_date) <> 0 Then
        is_date_in_workday_list = True
    Else
        is_date_in_workday_list = False
    End If
    
End Function

Function is_satday_or_sunday(ByVal in_date As Date) As Boolean
    Dim wd As Integer
    wd = Weekday(in_date)
    
    If wd = vbSunday Or wd = vbSaturday Then
        is_satday_or_sunday = True
    Else
        is_satday_or_sunday = False
    End If
    
End Function

Function get_next_workday(ByVal wd As Date) As Date
    wd = wd + 1
    
    While True
    
        If is_date_in_holiday_list(wd) Then
            wd = wd + 1
            
        ElseIf is_date_in_workday_list(wd) Then
            get_next_workday = wd
            Exit Function
        
        ElseIf is_satday_or_sunday(wd) Then
            wd = wd + 1
            
        Else
            get_next_workday = wd
            Exit Function
            
        End If
        
    Wend

End Function

Function calc_end_date(ByVal start_date As Date, ByVal cost_from_begin As Double, ByRef end_date As Date, ByRef cost_used As Double)

    end_date = start_date
    cost_used = cost_from_begin
    
    While cost_from_begin > 1
        cost_from_begin = cost_from_begin - 1
        cost_used = cost_used - 1
        end_date = get_next_workday(end_date)
    Wend

End Function

Function get_next_task(ByRef row_edit As Integer) As Boolean

    get_next_task = False
    
    Dim in_row As Integer
    in_row = row_edit
    
    Dim new_sort As Integer
    new_sort = 0
    
    Dim in_sort As Integer
    in_sort = Sheets(sheet_name_op).Cells(in_row, column_index_sort).value
    
    Dim target_sort As Integer
    Dim tmp_sort As Integer
    target_sort = 32767
    
    For i = 3 To end_row_holiday
        tmp_sort = Sheets(sheet_name_op).Cells(i, column_index_sort).value
        
        If tmp_sort > in_sort Then
            get_next_task = True
            
            If tmp_sort < target_sort Then
                target_sort = tmp_sort
                row_edit = i
            End If
            
        End If
    Next

End Function

Private Sub Worksheet_Change(ByVal Target As Range)

    If Target.Column <> column_index_start_date Then
        Exit Sub
    End If
    
    Dim cost_used As Double
    cost_used = 0

    Dim row_edit As Integer
    row_edit = Target.Row
    
    Dim row_edit_cost As Double
    row_edit_cost = Sheets(sheet_name_op).Cells(row_edit, column_index_cost).value
    
    Dim start_date As Date
    start_date = Sheets(sheet_name_op).Cells(row_edit, column_index_start_date).value
    
    'If start_date = "" Then
    '    MsgBox "have not input start date"
    '    Exit Sub
    'End If
    
    'if start_date is not workday then error

    cost_from_begin = row_edit_cost + cost_used
    
    Dim end_date As Date
    end_date = start_date
    
    calc_end_date start_date, cost_from_begin, end_date, cost_used
    Sheets(sheet_name_op).Cells(row_edit, column_index_end_date).value = end_date
    
    'next edit row
    While get_next_task(row_edit)
        
        start_date = end_date
        If cost_used >= 1 Then
            start_date = get_next_workday(start_date)
            cost_used = cost_used - 1
        End If
        
        Sheets(sheet_name_op).Cells(row_edit, column_index_start_date).value = start_date
        
        calc_end_date start_date, cost_from_begin, end_date, cost_used
        Sheets(sheet_name_op).Cells(row_edit, column_index_end_date).value = end_date
        
    Wend
    
End Sub

schedule.csv

No.,TaskName,,Cost,StartDate,EndDate,Man,Sort
1,TaskX,,3,,,,
2,,SubX1,1,2022/1/26,2022/1/27,Gu,2
3,,SubX2,2,,,Li,
4,TaskY,,5,,,,
5,,SubY1,2,,,Rui,
6,,SubY2,2,2022/1/24,2022/1/25,Gu,1
7,,SubY3,1,,,Rui,
8,TaskZ,,8,,,,
9,,SubZ1,3,,,Li,
10,,SubZ2,2,2022/1/29,2022/1/30,Gu,3
11,,SubZ3,3,,,Rui,

vba_pj_0001_auto_date的更多相关文章

  1. TCP/IP笔记(1)

    TCP/IP 背景和介绍 上世纪 70 年代,随着计算机技术的发展,计算机使用者意识到:要想发挥计算机更大的作用,就要将世界各地的计算机连接起来.但是简单的连接是远远不够的,因为计算机之间无法沟通.因 ...

随机推荐

  1. freertos内存pvPortMalloc 和 malloc 区别 ,以及全局变量占用情况

    1.FreeRtos占用内存 #define configTOTAL_HEAP_SIZE ( ( size_t ) ( 30 * 1024 ) ) pvPortMalloc是从configTOTAL_ ...

  2. Mybatis优化

    Mybatis优化 log4j日志显示 在pom.xml中的<dependencies>标签中加入 <!--log4j日志 --> <dependency> < ...

  3. wps二次开发

    JSAPI概述及原理 : [金山文档]JSAPI概述及原理 https://kdocs.cn/l/skWT29577eEE JSAPI集成开发文档 [金山文档]JSAPI集成开发文档 https:// ...

  4. 两行CSS让页面提升了近7倍渲染性能

    参考:https://juejin.cn/post/7168629736838463525 content-visibility.contain-intrinsic-size属性

  5. Android悬浮窗全屏不获取焦点但是可以漏出软键盘的办法

    addFlags( WindowManager.LayoutParams.FLAG_ALT_FOCUSABLE_IM);的作用是在不获取焦点的时候显示软键盘. 接触这个标记 getWindow().c ...

  6. WPF使用WindowChrome自定义标题栏

    第一步:基本实现 添加Window的Style定义,并设置WindowChrome.WindowChrome属性: 设置WindowChrome标题栏: CaptionHeight--主要用于拖动有效 ...

  7. ASP.NET Core 部署在Docker容器当中(1)

    一.前言 在公司新项目中,果断选择使用asp.net core,通过实践学习一系列技术栈:docker.docker-nginx.docker-compose.Jenkins,本文主要是介绍如何将项目 ...

  8. x-sheet 开发系列教程:初始化配置

    介绍 x-sheet 是一款高性能 Web JavaScript Canvas 电子表格,之前小编写过一篇 x-sheet 入门体验,简单介绍了一下如何使用 x-sheet.这次我们继续深入一下,了解 ...

  9. [BOM] 封装一下cookie

    function get_cookie(key) { var arr, reg = new RegExp("(^| )" + key + "=([^;]*)(;|$)&q ...

  10. Easyui 表格列数据合并!

    //datagrid调用列子 onLoadSuccess: function (data) { $(".datagrid-header-row").css("text-a ...