In any project, change is inevitable whether it comes from within the project or from external sources, therefore it makes sense to have an agreed process in order to identify, assess and control any potential and approved changes to what was originally agreed for the project.

What is needed is a systematic and common approach. Once the project plan and other key associated documents have been approved, these become the project "baselines" and can only be changed after approval by the appropriate authority, normally the Project Board. Change control is not there to prevent changes, but to ensure that every change is agreed by the relevant authority before implementation.

An important and vital element, is the projects use of configuration management (CM). Configuration management may be provided as a continuous organisational service or be provided by a Project Support Office (PSO). Everything that the project produces is subject to configuration management, this includes management documentation as well as specialist products and deliverables. It is important therefore to integrate the use of change control procedures with the configuration management system used by the project.

The system that is set-up to manage change should also include the management of the general issues. An Issue Register should be set up early in the project to capture and assist in the management of change and issues. A configuration management strategy document must be created as part of planning and this defines the way in which changes and issues are to be managed and handled throughout the project.

The difference between an issue and a risk is that the issue has already happened, whereas a risk is something that may or may not happen at some point in the future.

Whenever an issue is raised, it may be managed informally, usually by the project manager, however if it is to be managed formally then the project manager would enter it into the issue register before proceeding any further. The PRINCE2 methodology states that an Issue Report is created in tandem and contains supplementary information regarding that particular issue.

Changes come in two flavours:

Request For Change (RFC). This comes from the customer or user and is a request to change one of the project baselines in some way. If there are any extra costs involved in implementing the RFC, then the customer would normally pay for it. Since all RFC's are a change to what had been originally agreed, it is normally the Project Board alone will have the authority to agree such changes.

Off Specification. These are normally raised from the supply side of the project, and details some aspect that should be provided by the project, but currently is not, or is forecast not to be provided. This might include products or deliverables that are missing, or a product not meeting its specification or quality criteria.

At the beginning of a project it needs to be decided how changes and issues are to be prioritised, and it is usual that a ratings system might include terms such as, Must Have, Should Have, Could Have, or Won't Have For Now. Such definitions need to be agreed.

Another aspect that needs to be decided is whether or not the Project Board or senior management wanted to be involved in reviewing all project changes. If many changes are predicted then it may make sense for the Project Board to appoint a change authority who would make decisions on such changes on behalf of the Project Board. In such cases, the "rules of engagement" needs to be determined.

For example, the change authority would only deal with low cost changes. Another aspect is setting up a change budget for the change authority to use to fund any approved changes and their implementation. Such additional budgets should be captured within the project plan before sign-off.

Onwards to the change control procedure itself...

Step 1. Whenever a change or issue is raised, it should be categorised and entered in the issue/change register.

Step 2. An impact analysis should now be carried out and will normally involve relevant specialist team members.

The impact analysis should consider the change or issue impact (which may be positive or negative) on a variety of projects aspects such as:

  • Time
  • Cost
  • Quality
  • Scope
  • Business Case
  • Benefits
  • Risk

The change or issue should be prioritised, first, by the originator, and second, after impact analysis. It is important when carrying out the above impact analysis, that representatives from the project business area, the users of the end products, and those who are supplying resources to the project, are fully involved so that a balanced decision can be reached.

Step 3. Having understood the full impact of the change or issue, the next step is to consider alternative options and proposing the best actions to take in order to resolve the issue or implement the change. A balanced view is needed and consideration should be given all these options on the projects duration, cost, quality, scope, benefit, and risk performance targets. The advantages gained should be balanced against the impact of implementing the issue or change.

Step 4. A decision is now needed whether or not to implement the change. For a RFC, this would normally need escalating to the Project Board for their decision, whereas an Off-Specification may be decided by the project manager if they have sufficient authority.

If the project is using Management By Exception where tolerance boundaries have been set, then should any proposed implementation deviate beyond these tolerances, the Project Board must be involved in the decision whether to implement or not.

During implementation, the project manager should ensure that its status is reported to the Project Board up to the point when the issue or change has been fully implemented.

Using Change Management and Change Control Within a Project的更多相关文章

  1. Training - Problem and Change Management

    Problem Management Problem management seeks to identify the underlying causes of incidents in an IT ...

  2. input输入框的的input事件和change事件以及change和blur事件的区别

    input输入框的 oninput事件 ,在用户输入的时候触发,只要元素值发生变化就会触发 input输入框的 onchange事件 ,要在输入框失去焦点的时候触发事件,当鼠标在其他地方点击一下才会触 ...

  3. (IDEA) VCS-->Import Into Version Control没有Share Project(Subversion)这个选项。

    在VCS-->Import Into Version Control,会发现只有Import Into Subversion选项,并没有Share Project(Subversion)这个选项 ...

  4. SAP Change Request Management (ChaRM)基础教程

    本文介绍了SAP Solution Manager中的变更请求管理工具(Change Request Management,以下简称ChaRM ). 最近打算写个上线前请求号检查工具,为此需要了解相关 ...

  5. [ScreenOS] How to change the certificate that is used for SSL (HTTPS) WebUI Management

    SUMMARY: This article provides information on how to change the certificate that is used for SSL (HT ...

  6. [AX]AX2012 R2 采购订单的“Request change”

    在采购订单List或者Detail窗口的操作面板上有一个叫做“Request change”的按钮,如果这个按钮是激活的,采购订单不能直接编辑,而必须先使用这个按钮请求修改后,采购订单才能进入编辑状态 ...

  7. 【Gerrit】Gerrit cmd query (gerrit命令行查询change信息)

    本文仅展现个人使用情况和理解,英文原址:https://review.openstack.org/Documentation/cmd-query.html 基本使用格式: ssh -p <por ...

  8. $().change事件

    change([[data],fn]) 当元素的value值发生改变时发生change事件 适用于: 文本域 text textarea和select元素 text textarea 元素失去焦点时发 ...

  9. easyui给select控件绑定change事件

    一般的做法是使用jQuery来绑定,例如: $("#id").change(function(){ alert("change事件绑定"); }); 当给sel ...

随机推荐

  1. C#线程间同步无法关闭

    用C#做了个线程间同步的小程序,但每次关闭窗口后进程仍然在,是什么原因? 解决方法: 要加一句 线程.IsBackground = true; 否则退出的只是窗体 上面的方法没看懂... MSDN上说 ...

  2. chrome developer tool 调试技巧

    这篇文章是根据目前 chrome 稳定版(19.0.1084.52 m)写的, 因为 google 也在不断完善chrome developer tool, 所以 chrome 版本不同可能稍有差别. ...

  3. RETINA显示屏下ICON优化方法

    便于理解,先来了解几个名词: dpi(dots per inch),每英寸的点数,用来测量任何设备的硬件分辨率.一个21”的屏幕可以拥有1680 X 1050 的分辨率,27”的屏幕也可以拥有相同的分 ...

  4. 关于 Apple Metal API 的一些想法

    在看完 Metal 的开发文档后,除了官方所宣称的一些优点外(比如说更容易理解和使用的 API,更直接和精细的硬件控制,减少 GPU 使用过程中的 CPU 额外开销等等),从我有限的 GLES 开发经 ...

  5. 【BZOJ】1901: Zju2112 Dynamic Rankings(区间第k小+树状数组套主席树)

    http://www.lydsy.com/JudgeOnline/problem.php?id=1901 首先还是吐槽时间,我在zoj交无限tle啊!!!!!!!!我一直以为是程序错了啊啊啊啊啊啊. ...

  6. 【C语言】06-基本数据类型

    C语言有丰富的数据类型,因此它很适合用来编写数据库,如DB2.Oracle都是C语言写的. C语言的数据类型大致可以分为下图中的几类: 回到顶部 一.变量 跟其他语言一样,C语言中用变量来存储计算过程 ...

  7. win8 iis 安装

    win8下面安装iis跟win7一样,需要通过启用和关闭windouws功能来安装iis,具体要选哪些项,请看图: 如果要使用wcf服务,你还需要勾选以下项:

  8. Spring对加载的bean之间循环依赖的处理

    根据下面文档的叙述,简言之: 对于相互之间通过构造函数注入相互循环依赖的情况,Spring会抛出BeanCurrentlyInCreationException错误. 如果AB两个beans是通过属性 ...

  9. 2016.07.04,英语,《Vocabulary Builder》Unit 23

    text comes from a Latin verb that means 'to weave'. textile: ['tekstaɪl] adj. 纺织的 n. 纺织品; texture: [ ...

  10. Javascript 笔记与总结(2-3)Javascript 运算符、控制结构与对象操作

    [连接运算符 + ] <script> console.log(1+2+'a'+3+4); </script> 输出: 3a34 [逻辑运算符]返回的是最早能判断表达式结果的那 ...