recourse: "Software Engineering", Ian Sommerville


Keywords for this chapter:

  • planning
  • scheduling
  • cost estimation

Project planning takes place at three stages in a project life cycle:

  • At the proposal stage (When you are bidding for a contract to develop or provide a software system).

    • Do you have the resources to complete the work?
    • work out the price that you should quote to a customer.
  • During the project startup phase When you have to plan:
    • who will work on the project
    • how the project will be broken down into increments
    • how resources will be allocated across your company
    • etc
  • Periodically throughout the project

Planning at the proposal stage is inevitably speculative [ɪ'nevɪtəblɪ] ['spekjʊlətɪv] , as you do not usually have a complete set of requirements for the software to be developed. Rather, you have to respond to a call for proposals based on a high-level description of the software functionality that is required.

There are three main parameters that you should use when computing the costs of a software development project:

  • effort costs ( the costs of paying software engineers and managers)
  • hardware and software costs, including maintenance
  • travel and training costs

The plan should define project monitoring mechnisms. You must keep track of the progress of the project and compare actual and planned progress and costs.

Agood manager should be able to form a clear picture of what is going on through informal discussions with project staff.

1. Software pricing

When calculating a price, you should take the following iterms into account:

  • Market opportunity
  • Cost estimate uncertainty
  • Contractual terms
  • Requirements volatility
  • Financial health

1.1 market opportunity

A development organization may quote a low price because it wishes to move into a new segment of the software market. Accepting a low profit on one project may give the organization the opportunity to make a greater profit later. The experience gained may also help it develop new products.

1.2 Cost estimate uncertainty

If an organization is unsure of its cost estimate, it may increase its price by a contingency over and above its normal profit.

1.3 Contractual terms

A customer may be willing to allow the developer to retain ownership of the source code and reuse it in other prohects. The price charged may then be less than if the software source code is handed over to the customer.

1.4 Requirements volatility

If the requirements are likely to change, an organization may lower its price to win a contract. After the contract is awarded, high prices can be charged for changes to hte requirements.

1.5 Financial health

Developers in financial difficulty may lower their price to gain a contract. It is better to make a smaller than normal profit or break even than to go out of business. Cash flow is more important than profit in difficult economic times.

2. Plan-driven development

Plan-driven or plan-based development is an approach to software engineering where the development process is planned in detail.

2.1 Project plans

In a plan-driven development project, a project plan normally include the following sections:

  1. Introduction: This briefly describes the objectives of the project and sets out the constraints (e.g., budget, time, etc.) that affect the management of the project.
  2. Poject organization: This describes the way in which the development team its organized, the people involved, and their roles in the team.
  3. Risk analysis: This describes possible project risks, the likelihood of these risks arising, and the risk reduction strategies that are proposed.
  4. Hardware and software resource requirements
  5. Work breakdown: milestones and deliverables associated with each activity.
  6. Project schedul
  7. Monitoring and reporting mechanisms : This defines the management reports that should be produced, when these should be produced, and the project monitoring mechanisms to be used.

2.2 The planning process

The figure below is a UML activity diagram that shows a typical workflow for a project planning process.

contraints: delivery date, staff available, overall budget, available tools, and so on.

3. Project scheduling

Project scheduleing is the process of deciding:

  • how the work will be organized as separate tasks
  • when and how these tasks will be executed
  • calandar time
  • who will work on the tasks
  • resources needed

3.1 Schedule representation

Project schedules may simply be represented in a table or spreadsheet showing the tasks,effort, expected duration, and task dependencies.

There are two types of representation that are commonly used:

  • Bar charts: calendar-based, show who is responsible for each activity, the expected elapsed time, and when the activity is scheduled to begin and end. (Gantt charts)
  • Activity networks: network diagrams, show the dependencies between the different activities making up a project.

Project activities are the basic planning element. Each activity has:

  • a duration in clendar days or months
  • an effort estimate
  • a deadline
  • a defined endpoint. This represents the tangible result of completing the activity. This coud be a document, the holding of a review meeting, the successful execution of all tests, etc.

The table below shows tasks, estimated effort, duration, and task interdependencies.

It can be seen from the table that T3 is dependent on task T1. Task T1 must, therefore, be completed before T starts.

The bar chart below takes the information in table above and presents the project schedule in a graphical format.

Project managers have to allocate resources to tasks as well.

The table below shows when staff are working on the project.

4. Agile planning

Agile methods of software development are iterative approaches where the software is developedand delivered to customers inincrements.

(important but skip here)

Software Engineering: 3. Project planning的更多相关文章

  1. SENG201 (Software Engineering I) Project

    SENG201 (Software Engineering I) ProjectSpace ExplorerFor project admin queries:For project help, hi ...

  2. Software Engineering: 2. Project management

    resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...

  3.  Go is more about software engineering than programming language research.

    https://talks.golang.org/2012/splash.article Go at Google: Language Design in the Service of Softwar ...

  4. 第二篇——The communication during software engineering.

    I've learned a lot in my software engineering class about how a program comes out.That's also a esse ...

  5. 2.2 CMMI2级——项目计划(Project Planning)

    大家都明白这样的一个道理:做事情要有计划,有一个不成熟的计划总比没有计划要好,软件开发这么复杂的活动,更加需要计划.那么应该怎样做好一个计划呢? 如果对项目的范围.规模.性质.任务.工作量.费用等都不 ...

  6. Software Engineering: 1. Introduction

    Resource: Ian, Sommerville, Software Engineering 1. Professional software development 1.1 Software e ...

  7. 个人阅读作业2—《No Silver Bullet: Essence and Accidents of Software Engineering》读后感

    在进行了一次结对编程.一次团队编程和一次个人编程项目后,读了<No Silver Bullet: Essence and Accidents of Software Engineering> ...

  8. Software Engineering at Google

    Google的Fergus Henderson在Software Engineering at Google中介绍了Google的软件工程实践. 软件开发 源码仓库 单一源代码仓库,除了核心配置和安全 ...

  9. Limeng:Individual Project: Word frequency program -BUAA Advanced Software Engineering

    11061190-李孟 Implement a console application to tally the frequency of words under a directory (2 mod ...

随机推荐

  1. tomcat

    引用:http://blog.csdn.net/nairuohe/article/details/6175243 /etc/tomcat6 - 全局配置 /usr/share/tomcat6/ - 程 ...

  2. Hadoop: Hadoop Cluster配置文件

    Hadoop配置文件 Hadoop的配置文件: 只读的默认配置文件:core-default.xml, hdfs-default.xml, yarn-default.xml 和 mapred-defa ...

  3. PHP基础班初学感悟

    不知不觉差不多一个月就过去了 刚到培训班那时候的心情,现在也还能有所感觉 作为今年6月份的毕业生,刚从大学的实习期出来,辞掉了上一份工作,本来是打算找一份更加与专业挂钩的工作做的 也许是90后对网络的 ...

  4. Time crumbles things; everything grows old under the power of Time and is forgotten through the lapse of Time

    Time crumbles things; everything grows old under the power of Time and is forgotten through the laps ...

  5. 基于bootstrap 的datatable插件的使用2(php版)

    DataTables 中有两种不同的方式处理数据(排序.搜索.分页等): 客户端处理(Client)-- 所有的数据集预先加载(一次获取所有数据),数据处理都是在浏览器中完成的[逻辑分页]. 服务器端 ...

  6. style设置/获取样式的问题 和 offsetWidth/offsetHeight的问题

    style设置/获取样式的问题:1.js通过style方法    --加样式:加的是行间样式 oDiv.style.width="20"+'px';    --取样式:取得是行间样 ...

  7. C++内存泄露之野指针

    写出本文仅仅是处于备忘的目的. 最近为现在做的软件添加了一个内存回收机制(以前处于某种内存只申请不释放,这并不等于内存泄露,因为我们知道这些内存块在内存中的位置)-- 在某一块内存不使用的时候将其释放 ...

  8. 一个ubuntu phper的自我修养(杂记)

    ubuntu使用杂记 1.flatabulous安装使用. flatabulous是一个ubuntu图标主题. 使用它,必须得安装tweak插件. sudo add-apt-repository pp ...

  9. [Spark] Spark的RDD编程

    本篇博客中的操作都在 ./bin/pyspark 中执行. RDD,即弹性分布式数据集(Resilient Distributed Dataset),是Spark对数据的核心抽象.RDD是分布式元素的 ...

  10. androi 多线程

    <LinearLayout xmlns:android="http://schemas.android.com/apk/res/android" xmlns:tools=&q ...